LOCATION: Seafolly, Chadstone

Seafolly's defit at Chadstone Shopping Centre was conducted exclusively after operating hours, with a timeframe of 7 days allocated for completion.

The task involved stripping the premises down to its bare shell, including the challenging removal of cladding from entrance columns using a jackhammer. The scope of work encompassed dismantling all shop fittings, joinery, floor grinding, ceiling removal, partition walls, shop front, and floor coverings.

The Melbourne Defit Company team demonstrated exceptional efficiency in completing the project ahead of schedule and within budget constraints.

Last updated on Saturday, April 6th 2024